Case Study 1: Koshi Riverbank Protection Project, Sunsari District

Client: Government of Nepal (Department of Water Resources & Irrigation)
Contractor: Nepalese Civil Engineering Consortium
Chinese Machine Used: Double-Twist Gabion Weaving Machine (Model: GT-4.0, 415V/50Hz compatible)

Challenge:

Severe riverbank erosion along the Koshi River threatened agricultural land and villages during monsoon floods. Importing pre-made gabions was costly and logistically slow.

Solution & Machine Role:

  • The contractor purchased a Chinese double-twist machine to produce gabion mesh locally (spec: 80x100mm mesh, 2.7mm PVC-coated wire).

  • Machine Performance:

    • Operated 10 hours/day under Nepal’s grid instability (voltage fluctuations: 360V–440V), supported by an external stabilizer.

    • Output: 30–35 m²/hour (6,000+ m² produced in 8 weeks).

    • Double-take-up system allowed continuous production during spool changes.

  • Local Impact:

    • Trained 5 Nepali operators (basic maintenance included).

    • Reduced project cost by 18% vs. importing gabions.

Outcome:

5.2 km of riverbank reinforced before monsoon. Erosion reduced by >70% post-floods.


Case Study 2: Kathmandu Outer Ring Road Slope Stabilization

Client: Nepal Roads Authority (DoR)
Contractor: Sino-Nepal Infrastructure JV
Chinese Machine Used: Semi-Automatic Gabion Loom (Model: XG-200, altitude-optimized)

Challenge:

Stabilizing landslide-prone slopes along a new highway section near Kathmandu (1,400m altitude). Tight deadlines demanded on-site production.

Solution & Machine Role:

  • Machine installed in a temporary site factory.

  • Produced custom-sized gabion mattresses (100x120mm mesh, 2.2mm Galfan wire).

  • Key Adaptations:

    • Dust-proof electrical cabinets (IP54) handled construction-site debris.

    • PLC-controlled length counting (±0.5% accuracy) minimized wire waste.

    • Operated 24 days non-stop (maintenance: 1 breakdown for bearing replacement).

  • Logistics Advantage:

    • Saved $15,000/month in transport vs. shipping gabions from India.

Outcome:

Completed 8,500 m² of slope protection on schedule. Structure integrity passed DoR inspections.


Case Study 3: Gandak Irrigation Canal Rehabilitation, Nawalparasi

Client: FAO Nepal (UN-funded project)
Contractor: Local NGO Cooperative
Chinese Machine Used: Portable Gabion Weaving Unit (Model: Mini-Twist MT-100)

Challenge:

Repairing eroded canal sections in a remote area with limited electricity (solar/diesel hybrid power). Low technical skill availability.

Solution & Machine Role:

  • Deployed a compact Chinese machine powered by 8kVA generator.

  • Produced 60x80mm mesh (2.0mm PVC-coated wire) for small gabion sacks.

  • Simplified Workflow:

    • 1-day operator training (basic threading, HMI operation).

    • Manual spool loading (no crane needed).

    • Output: 15 m²/hour (sufficient for daily repair targets).

  • Community Impact:

    • Employed 12 local workers (50% women).

    • Machine still used 3 years later for maintenance.

banner
Blog Details
Created with Pixso. Home Created with Pixso. Blog Created with Pixso.

Sunrich gabion machines were successfully used for the projects, challenges, solutions, and the role in Nepal

Sunrich gabion machines were successfully used for the projects, challenges, solutions, and the role in Nepal

Case Study 1: Koshi Riverbank Protection Project, Sunsari District

Client: Government of Nepal (Department of Water Resources & Irrigation)
Contractor: Nepalese Civil Engineering Consortium
Chinese Machine Used: Double-Twist Gabion Weaving Machine (Model: GT-4.0, 415V/50Hz compatible)

Challenge:

Severe riverbank erosion along the Koshi River threatened agricultural land and villages during monsoon floods. Importing pre-made gabions was costly and logistically slow.

Solution & Machine Role:

  • The contractor purchased a Chinese double-twist machine to produce gabion mesh locally (spec: 80x100mm mesh, 2.7mm PVC-coated wire).

  • Machine Performance:

    • Operated 10 hours/day under Nepal’s grid instability (voltage fluctuations: 360V–440V), supported by an external stabilizer.

    • Output: 30–35 m²/hour (6,000+ m² produced in 8 weeks).

    • Double-take-up system allowed continuous production during spool changes.

  • Local Impact:

    • Trained 5 Nepali operators (basic maintenance included).

    • Reduced project cost by 18% vs. importing gabions.

Outcome:

5.2 km of riverbank reinforced before monsoon. Erosion reduced by >70% post-floods.


Case Study 2: Kathmandu Outer Ring Road Slope Stabilization

Client: Nepal Roads Authority (DoR)
Contractor: Sino-Nepal Infrastructure JV
Chinese Machine Used: Semi-Automatic Gabion Loom (Model: XG-200, altitude-optimized)

Challenge:

Stabilizing landslide-prone slopes along a new highway section near Kathmandu (1,400m altitude). Tight deadlines demanded on-site production.

Solution & Machine Role:

  • Machine installed in a temporary site factory.

  • Produced custom-sized gabion mattresses (100x120mm mesh, 2.2mm Galfan wire).

  • Key Adaptations:

    • Dust-proof electrical cabinets (IP54) handled construction-site debris.

    • PLC-controlled length counting (±0.5% accuracy) minimized wire waste.

    • Operated 24 days non-stop (maintenance: 1 breakdown for bearing replacement).

  • Logistics Advantage:

    • Saved $15,000/month in transport vs. shipping gabions from India.

Outcome:

Completed 8,500 m² of slope protection on schedule. Structure integrity passed DoR inspections.


Case Study 3: Gandak Irrigation Canal Rehabilitation, Nawalparasi

Client: FAO Nepal (UN-funded project)
Contractor: Local NGO Cooperative
Chinese Machine Used: Portable Gabion Weaving Unit (Model: Mini-Twist MT-100)

Challenge:

Repairing eroded canal sections in a remote area with limited electricity (solar/diesel hybrid power). Low technical skill availability.

Solution & Machine Role:

  • Deployed a compact Chinese machine powered by 8kVA generator.

  • Produced 60x80mm mesh (2.0mm PVC-coated wire) for small gabion sacks.

  • Simplified Workflow:

    • 1-day operator training (basic threading, HMI operation).

    • Manual spool loading (no crane needed).

    • Output: 15 m²/hour (sufficient for daily repair targets).

  • Community Impact:

    • Employed 12 local workers (50% women).

    • Machine still used 3 years later for maintenance.